LovelandTuesday, November 10

Loveland has finished its $24.5 million Fourth Street rebuild ahead of the holidays

The Good Day Fort Collins teamFrom Tuesday’s edition · 1 min read · 2 sources

ShareEmailFacebookX

If you've been steering around downtown Loveland, you can stop. The city says construction has wrapped up on five blocks of Fourth Street between North Washington and Garfield avenues. The Heart Improvement Plan, known as , began in February 2025.

No General Fund dollars paid for the $24.5 million Fourth Street project

Loveland's HIP Streets project, $24.5 million, by where it comes from and where it goes

Comes from

$24.5 million

Goes to

$12M City utility enterprise funds 49%$12.5M DDA-paid certificates 51%
$24.5M Fourth Street rebuild 100%

Comes from

  • $12M City utility enterprise funds 49%
  • $12.5M DDA-paid certificates 51%

$24.5 million

Goes to

  • $24.5M Fourth Street rebuild 100%

Sources: North Forty News, BizWest

View as table
AmountShare
From: City utility enterprise funds$12 million49%
From: DDA-paid certificates$12.5 million51%
To: Fourth Street rebuild$24.5 million100%

Crews also replaced aging pipes below the street, including cast-iron water pipes more than a century old and clay stormwater connections. Downtown keeps the same number of parking spaces.

  • Above ground: wider sidewalks with brick pavers, new lighting, trees and boulder seating
  • Art: 10 "" sculptures by Jen Lewin, two per block
  • Ribbon-cutting: planned after the sculptures go in
  • More info: lovgov.org/HIPStreets

Fourth Street's rebuild ends and the art arrives next

  1. Feb. 2025Construction on Fourth Street begins.
  2. Nov. 2026The city announces construction has wrapped up on five blocks.
  3. Spring '27Ten sculptures will be installed, two per block.

Sources: North Forty News, BizWest

Read it in the full edition

More from Tuesday’s edition

Read the edition
All getting around news
  1. The Sum and Substance12 hours ago

    With sales-tax increase for passenger rail approved, officials getting to task of building out Colorado Connector, on The Sum and Substance

    The Front Ranger Passenger Rail is slated to begin service with three round trips daily between Fort Collins and Denver by 2029/